8 Novena Drive
Repair Project

8 Novena Drive

Magtech General Construction & Trading Pte Ltd carried out an FRP water tank repair at 8 Novena Drive, Singapore, replacing a single cracked side panel on a make-up water tank.

FRP water tank panel repair at 8 Novena Drive Singapore - cracked panel marked before removal
Cracked panel marked before removal

PROJECT INFORMATION

PROJECT OVERVIEW

Tank inspection

A leak had been reported, and our team attended site to trace it.

The inspection found a crack in one panel. Only that panel was affected, and the rest of the tank – the surrounding panels, the framework and the internal fittings – was sound. On its own that is good news, because it meant a full tank replacement could be avoided.

The complication was where the cracked panel sat. It was the lowest tier side panel, at the bottom of the tank wall, which carries the greatest head of water and sits underneath every panel above it. A panel in that position cannot simply be unbolted and swapped. The sections above it had to be carefully taken down first, the cracked panel released and replaced, and the tank then rebuilt in the correct sequence. That is work for experienced technicians rather than a straightforward part swap.

01
Scope of work
  • Attendance on site to trace the reported leak
  • Inspection of the tank and identification of the cracked panel
  • Controlled draining of the tank
  • Careful dismantling of the tank sections above the affected panel
  • Removal of the cracked FRP side panel
  • Supply and installation of a matching replacement panel
  • Resealing of panel joints and re-tightening of fixings
  • Reinstallation of the dismantled sections
  • General site cleaning on completion
  • Testing and reinstatement for service
02
Project outcome
  • Reported leak traced to a single cracked FRP panel
  • Only the affected panel replaced; the rest of the tank retained
  • Lowest tier panel replaced without damage to the surrounding panels
  • Full tank replacement avoided
  • Make-up water tank rebuilt, tested and returned to service

Our Approach

1. Leak Investigation and Inspection

Our team attended site to trace the reported leak and inspected the tank to establish where the water was escaping. The source was a crack in a single side panel.

2. Assessing the Position of the Panel

The cracked panel was in the lowest tier of the tank wall. That position carries the greatest water pressure and sits beneath the panels above it, so replacing it meant partially dismantling the tank rather than removing one panel in isolation.

3. Controlled Dismantling and Panel Replacement

The tank was drained and the sections above the affected panel were taken down in a controlled sequence, so that the surrounding panels, seals and fixings were not damaged in the process. The cracked panel was then removed and a matching replacement installed.

4. Reinstallation, Testing and Reinstatement

The dismantled sections were rebuilt in the correct order, joints resealed and fixings re-tightened. The tank was refilled and checked for leaks, and the working area was cleaned down before handover.

 

Why This Matters

A cracked panel does not always mean a new tank, but where the panel sits changes the job completely. A crack in an upper panel can often be reached with very little disturbance. The lowest tier is different: it carries the full head of water and every panel above it rests on that line, so the tank has to be partially taken down and then rebuilt correctly before it can hold water again.

Getting that sequence right, without damaging the panels and seals that are still perfectly good, is what separates a one-panel repair from a job that turns into a full replacement. It is the reason this kind of work goes to installers who have done it before.

With over 35 years of experience and more than 4,000 water tanks installed across Asia, Magtech continues to deliver FRP water tank repair and replacement for buildings across Singapore.

35+

Years of experience

in sectional water tanks

4,000+

Tanks installed

across Singapore and Asia

Our team will respond within 24–48 hours.

NEED A FASTER RESPONSE? WhatsApp Our Team
PROJECT GALLERY

Repair Photos

DISCUSS YOUR PROJECT

Enquire About 8 Novena Drive Tank Installation, Replacement or repair

Send us the required effective capacity, available space, intended water use and project drawings. Our team can review the information and advise on the next step.

Our team will respond within 24–48 hours.

NEED A FASTER RESPONSE? WhatsApp Our Team

Other related projects

Project: 24A Senoko Road

Project: Margaret Villa

Project: Changi Cove